Powerdot stays at 11,500 charging points and blames red tape for delays

Powerdot stays at 11,500 charging points and blames red tape for delays
Image: ECO

Powerdot set a target of 14 thousand charging points for 2025 and missed it, and what held it back most, says its CEO, was not electricity...

The company expected to install each station in 12 to 18 months, but some, in Spain, took five years.

01

What happened

The target Powerdot set in 2022 was to reach 14 thousand charging points by the end of 2025. The year ended with 11,500. Co-founder and CEO Luís Santiago Pinto admitted to ECO, on the sidelines of Web Summit, that the company was too optimistic about installation times.

In Spain, he said, some stations took five years, when the initial expectation was 12 to 18 months.

02

What is behind it

According to Luís Santiago Pinto, the biggest drag is the bureaucratic process, not the power available. He says the question of grid capacity will end up being solved, with batteries or without them. The source is cut off mid-way and does not explain what the company is now doing with the batteries.

03

What this may change for you

Four kinds of business, four readings.

Large company

If you run a large company or a multinational

Powerdot set a target of 14 thousand charging points in 2022 and ended 2025 with 11,500. If your plan involves opening many sites, the CEO points to bureaucratic process as the biggest brake, so it may be worth counting on that time in your numbers.

SME

If you have an SME

According to the CEO, some stations in Spain took five years, when the company expected 12 to 18 months. If an investment of yours depends on a licence, it may be worth talking to your accountant about what happens if approval takes longer than expected.

Startup or self-employed

If you are a startup founder or work for yourself

The CEO admitted that Powerdot was optimistic about installation time. If your start date depends on a permit you do not control, an optimistic forecast may delay the rest of what you have planned.

Local business

If you have a small local business, like a bakery or a shop

The source talks about a charging operator and says nothing about small businesses. If you plan to install chargers at your premises, the CEO shows that timelines may slip a lot, but the source does not say whether this applies to small installations.

04

What you can take from this

If your plan depends on a licence or an authorisation, I would start by asking the body that decides how long it usually takes, and I would plan with a margin. An optimistic forecast can delay everything else. Which deadline in your plan depends on an approval you do not control?

Tell me what you thought

It is anonymous, one rating per person, and it helps me decide what to keep and what to cut.

Was it useful to you?
Did it feel fair and balanced?

Source

Radar briefs are written with the help of artificial intelligence, in the Desmonta style, from articles by other outlets, and checked by automatic rules and by a second independent check. They can contain mistakes: always confirm at the original source.

If you own the rights to the image and want it removed, tell us on the contact page. Contact

If you like this, get one real business story per issue.

It is free.

Subscribe